Deck Permits in East Marlborough Township, PA

TL;DR: East Marlborough Deck Permits at a Glance

  • Every deck needs a building permit. No size or height exemption here. You’ll also need a zoning permit.
  • The deck permit starts at $500. Start work without one, and all your fees double.
  • Mind the R-B numbers. A deck can reach 6 feet into a side yard and 20 feet into a rear yard, and only 10% of your lot can be covered.
  • Unionville has an extra step. Homes in the historic overlay need a certificate of appropriateness before work starts.
  • Dig deep. The township’s design criteria call for footings at least 36 inches below grade.

 

Ask around Pennsylvania, and somebody will tell you a low deck doesn’t need a building permit.

In most townships, they’re right. Pennsylvania’s Uniform Construction Code (UCC) skips the building permit for an uncovered deck that sits 30 inches or less above the ground.

East Marlborough Township isn’t like most townships. Here, every deck needs a building permit, even one that’s a foot off the grass.

And that’s only the first surprise. Big-lot setbacks, a 10% coverage cap, and a historic overlay around Unionville village can all change what you’re allowed to build and where.

Sure, it’s a lot to keep track of, but we’re here to help. We’re Keystone Custom Decks, and we’ve been building decks in Pennsylvania for over 40 years, including right here in Chester County. Below, we’ll walk through what East Marlborough publishes about deck permits and where we see projects lose the most time. Every source is linked so you can check our work.

Following is everything you need to know about getting a permit to build a deck in East Marlborough Township, located in the heart of Chester County.

Do You Need a Permit for a Deck in East Marlborough?

Yes. Every time.

The township’s construction code repealed the state’s deck exemption in 2004, so any deck, regardless of size or height above grade, needs a building permit before construction starts. The township also requires a residential zoning permit for decks, so plan on both.

Why bother with a deck that’s barely off the ground? Most attached decks hang off a ledger board bolted to the house. If that connection isn’t flashed and fastened correctly, water can work its way into your home’s framing and start rotting it. That happens whether the deck sits one foot up or ten.

The township’s permit list also includes patios and hot tubs, so mention those up front if they’re part of the plan.

What a Deck Permit Costs in 2026

East Marlborough adopted its current fee schedule, Resolution 2026-18, on March 11, 2026. Here are the line items most likely to affect your deck:

Item Fee
Deck permit $500
Roofed or enclosed deck Additional $225
Adding a stairway to an existing deck $230
Failed or not-ready inspection $200 per visit
Pennsylvania UCC fee $4.50 per building permit
Starting work before permits are issued All fees doubled

 

Keep in mind that these are minimums, and “additional fees may apply.” Some projects also need a Professional Services Agreement to cover engineering review.

Paying the fee is the easy part, though. Here’s where East Marlborough deck projects tend to get stuck:

1. Designing Before You Check Your Setbacks

East Marlborough is known for its roomy lots, and the zoning code reflects it. Take the R-B Residential District. Lots need at least 80,000 square feet (a little under two acres), and the required setbacks for your home are:

  • 75 feet in front
  • 35 feet minimum on each side (75 feet combined)
  • 60 feet in the rear

Decks get a little extra room. A deck can project up to 6 feet into a required side yard and up to 20 feet into a rear yard. On an R-B lot, that means your deck can come within 29 feet of a side property line and 40 feet of the rear one.

Unroofed porches get less, as they can only project 6 feet into any required yard, including the rear.

So what’s the difference between a deck and an unroofed porch? The township doesn’t define either one. In everyday terms, an unroofed porch is an open platform attached to the house with no roof overhead, which sounds a lot like a deck. The call could come down to your design, so ask how the township will classify your project before you finalize it.

Not in the R-B district? Other districts and cluster lots follow different numbers, so confirm yours first.

2. Running Out of Lot Coverage

In the R-B district, only 10% of your lot can be covered by things like your house, driveway, and patios. On a minimum-size lot, that’s 8,000 square feet.

That sounds like plenty. But a big house, a long driveway, and a pool can use it up real quick.

So does a deck count? The township’s stormwater rules don’t count a deck with gaps between the boards, since rain falls right through. The zoning rules aren’t as clear. If your lot is already pretty built-out, ask the Zoning Officer before you finalize your design.

Stormwater can come up on its own, too. Projects with 500 square feet or more of regulated impervious surface fall under the township’s stormwater requirements. A gapped deck usually won’t count, but a concrete patio poured underneath it can.

East Marlborough Township Deck Permits

3. Missing the Unionville Historic Review

If you live in or around Unionville village, you already know it takes some effort to keep the place looking the way it does.

The Historic District overlay covers roughly 120 acres in and around the village, along Route 82, Route 162, and Wollaston Road. Inside it, you’ll need a certificate of appropriateness from the Board of Supervisors before work begins, in addition to your building permit.

The review focuses on what can be seen from a public street. A deck tucked behind the house may be a simpler conversation than one facing the road, but you’ll need to work with the township before you build either one.

Deck Permits in East Marlborough Township

4. Turning In an Incomplete Permit Packet

East Marlborough conveniently bundles zoning and building into one residential permit packet. For a deck, plan on submitting:

  • A residential zoning permit with a sketch “showing the plot plan, existing structures, and proposed construction”
  • A building permit application
  • Two sets of construction plans
  • A Property Owner’s Certification and Indemnity form
  • A workers’ compensation affidavit (proof of your contractor’s coverage, or a notarized exemption)
  • A soil and erosion plan, if your project needs one. A grading permit is required once 500 square feet or more of earth is disturbed.

You can email the packet or drop it off at the Township Office at 721 Unionville Road in Kennett Square, open weekday mornings from 8:30 to noon. Once your application is complete and fees are filed, the Zoning Officer has 15 days to issue or deny the zoning permit. Payment comes after the permit is issued, not before.

How To Get A Deck Permit in East Marlborough Township

One more thing: read the indemnity form before you sign it. By signing, you certify the deck will be built “strictly in accordance with” the UCC. You also agree to hold the township harmless if anyone later claims it wasn’t, even if an inspector missed a defect. In other words, the permit doesn’t make your deck the township’s responsibility. It stays with you and your builder.

5. Failing Code Checks and Inspections

As of January 1, 2026, Pennsylvania enforces the 2021 International Residential Code (IRC). East Marlborough also publishes its own climatic and geographic design criteria, the numbers your deck plans are designed around:

  • Ground snow load: 30 pounds per square foot
  • Wind speed: 115 mph
  • Frost line depth: 36 inches
  • Weathering: severe
  • Termite risk: moderate

That 36-inch frost depth is the one to take seriously. Chester County’s freeze-thaw cycles can heave a shallow footing in just a few winters.

These code items come up on almost every deck we build:

  • Ledger: The ledger needs flashing so water can’t get behind it and into your home’s framing.
  • Lateral load connections: Hold-down devices tie the deck to the house. You’ll need two rated at 1,500 pounds within 24 inches of each end, or four rated at 750 pounds.
  • Hardware: Fasteners and connectors need to be hot-dip galvanized, stainless, or another approved corrosion-resistant type.
  • Guards: Any walking surface more than 30 inches above grade needs a guard at least 36 inches high, with openings small enough that a 4-inch sphere can’t pass through.
  • Stairs: Pennsylvania sets its own numbers: risers no taller than 8¼ inches and treads at least 9 inches deep. Four or more risers means you need a handrail.

Then come the inspections. East Marlborough doesn’t publish a deck-specific checklist, but its fee schedule names three stages:

  • Footings, before any concrete is poured
  • Framing, before deck boards cover the structure
  • Final, before anyone uses the deck

The inspectors don’t mess around, either. If they show up to a failed or unfinished stage, that’s a $200 fee, and you must pay it before the next inspection is scheduled. The township doesn’t have an online scheduler, so call the Building Inspector/Zoning Officer at (610)220-9294 or the inspector listed in your permit packet.

What Happens If You Build Without a Permit?

It’s tempting to cut a couple of corners while saving a few bucks, but when, and not if, you get busted, it’s going to cost you.

East Marlborough doubles every fee for work started without permits. Zoning violations are enforced through Pennsylvania’s Municipalities Planning Code, which allows judgments of up to $500 per violation plus court costs and attorney fees. Each day counts as a separate violation, so a month of an unpermitted deck can add up fast. The township can also go to court to stop or remove unlawful construction.

Then there’s the practical side. An inspector can’t see footings buried in concrete or framing hidden under deck boards, so you may have to dig up or tear out finished work just to have it checked. Unpermitted work can also come back to bite you when you sell your home.

Just don’t do it. You’ll be on the township’s naughty list for a long time, and it’ll come back to haunt you when you sell your home.

Your 5-Step East Marlborough Permit Checklist

Most permit delays come down to doing things in the wrong order. Here’s the order to follow:

  1. Confirm your zoning district and whether you’re in the Unionville historic overlay.
  2. Check setbacks and lot coverage before you settle on size and location.
  3. Design to the township’s criteria, including 36-inch footings and the 2021 IRC.
  4. Submit the full permit packet, and read the indemnity form before you sign.
  5. Schedule each inspection before the work gets covered up.

When you build with us, every step on that list is our job. We start with a complimentary 3D rendering, so you can see the deck on your house before you sign anything. Our limited lifetime workmanship warranty backs every deck we build, and we’ve been building across Chester County, Unionville, and Kennett Square for over 30 years.

To get started, reach out to our team or call 717-356-3858. We’ll help you figure out what your deck needs before you commit to anything.

Helpful Resources

Need those links again? Here they are, all in one spot:

Disclaimer

While the information in this blog has been researched to the best of our knowledge, it’s important to note that:

  • The information is gathered from publicly available online sources
  • Permitting rules and requirements can change or vary by township
  • It is always best for the homeowner to confirm directly with their local township or permitting office before starting construction.